monitoring_1.jpeg
rvca-slide_01.jpg
rvca-slide_02.jpg
rvca-slide_03.jpg
rvca-slide_04.jpg
rvca-slide_05.jpg
rvca-slide_06.jpg
rvca-slide_07.jpg
rvca-slide_08.jpg
rvca-slide_09.jpg
rvca-slide_10.jpg
rvca-slide_11.jpg
rvca-slide_12.jpg
January 09, 2020

Review Process

Super User

RVCA staff will review the application and discuss it with the applicant. Staff may suggest changes in the plan so it will comply with environmental rules and regulations. At the end of the review, recommendations will be sent to the municipality for its consideration in its decision.

January 09, 2020

Pre-Consultation Process

Super User

The RVCA and our member municipalities encourage pre-consultation in advance of submitting a formal Planning Act application. At a pre-consultation meeting, the applicant, the approval authority and the review agencies will discuss the proposal and the reports that may be necessary to support the application. The pre-consultation process assists the applicant in preparing a proposal that will meet the policies and submission requirements of the municipality, the RVCA and other agencies, potentially saving time and money.

January 09, 2020

Types of Applications

Super User

The applications reviewed by the RVCA include:

  • plans of subdivision and condominium
  • severances
  • minor variances
  • comprehensive zoning by-laws and zoning by-law amendments
  • official plans and official plan amendments
  • site plans
  • lifting of reserves

The RVCA also participates on technical advisory committees that oversee the preparation of broader planning studies such as community design plans, master servicing studies, environmental management plans and environmental assessments. We also review applications and provide advice on applications that are submitted under the Aggregate Resources Act.

January 06, 2020

Customer Service Charter

Super User
File   
Customer Service Charter Download

Laura Cummings

Additional Info

2020 Budget and Work Plan

ATR - November-December 2019

December 2, 2019 – Local Conservation Authorities are pleased with the findings of the independent review of the Spring 2019 flood. Retained by the Ontario Government, Special Advisor on Flooding Douglas NcNeil recognizes Ontario’s unique watershed-based Conservation Authority model and its success in minimizing flood risks and mitigating flood impacts. Ottawa area Conservation Authorities (Mississippi, Rideau and South Nation) met with Mr. McNeil and other agencies in September to review the spring flood and discuss local experiences. Ideas were shared on how to improve protection of Ontario residents and their properties from flooding. The McNeil report contains 66 actions, and the…
November 19, 2019

Stillwater Creek Stabilization Project

Super User

Stillwater Creek Slope Stabilization Project

RVCA was contracted by the City of Ottawa to design and implement remediation of an eroded bank of Stillwater Creek adjacent to Nautica Private and Carling Avenue and into the Ottawa River. Erosion of the slope is being caused by fluctuating flow and velocity in the creek and this project will help prevent potential slope failure.

Erosion 1 copy   Erosion 2
East Bank Erosion    East Bank Erosion 

The headwaters of Stillwater Creek begin in the National Capital Commission’s Stoney Swamp. Stoney Swamp is almost 2000 hectares in size, and is a mix of woodland, wetland and regenerating fields. From Stoney Swamp, Stillwater Creek runs through a heavily channelized and impacted area adjacent to Robertson Road. The creek turns into its natural morphology downstream of Robertson Road until the Highway 417 crossing. It then becomes channelized again, as it runs through Wesley Clover Park on Corkstown Road. The creek flows through another large wetland before Moodie Drive crossing, and from there runs parallel between Highway 417 and Corkstown Road until it turns north flowing through residential neighborhoods before emptying into the Ottawa River between the Nepean Sailing Club and Andrew Haydon Park.

The first phase to be completed is on the west bank of the creek in the treed area. The highlighted blue area is the East bank portion of the work to be completed as the second phase.

Map of work area
Map of the Work Area

Further erosion of the bank of Stillwater Creek at Nautica Private could be detrimental to the properties on Nautica Private and to the safety of the residents. 

Rock Toe Berm Construction

RVCA looked into multiple alternatives for the slope stabilization of the banks of Stillwater Creek. RVCA decided on the construction of a rock toe berm to stabilize the east bank of the creek. Once the design was complete, RVCA had it checked by a third-party local geotechnical engineering firm.

The rock toe berm has been designed to make a “key” at the base of the slope to be filled with large “rock protection” sized stones. The slope will then be backfilled at a 1.5:1 (h:v) slope and the large stones will extend above the creeks assumed 100-year flood elevation. The work is expected to protect the properties on Nautica Private from further property damage due to erosion.

Timing

The project took place from approximately December 22019 – February 28, 2020.

Project Partners

City of Ottawa
Rideau Valley Conservation Authority

Information

Terry K. Davidson, P.Eng.
Director of Engineering & Regulations

Page 28 of 82

Contact Us

Address:
Rideau Valley Conservation Authority
3889 Rideau Valley Drive
Manotick, Ontario K4M 1A5

Phone:
613-692-3571, 1-800-267-3504

Email:

Hours:

Regular Hours: Monday to Friday, 8:30 a.m. to 4:30 p.m.

Member of: conservation ontario